Cabling works by HK Electric 港燈電纜重鋪工程

30/9/2022

 
Picture
[30 September 2022]
HK Electric hope to finish stage 1 works by Q1 of 2023 and to finish the entire programme by 2024 (tentatively). 

港燈預計第一期工程會於2023年第一季完成,他們希望於2024年完成整項工程。


[12 Jan 2022]
​To follow up on an earlier report (
link), we met with HK Electric engineers to learn about their programme to enhance power supply to the Pok Fu Lam area. The related road works are divided into various sections (link). They expect to finish the Sassoon Road section in February 2022. 

繼早前報導後(
連結),我們與港燈的工程師會面,以了解港燈改善區內供電網絡的計劃,他們會分階段進行掘路工程(連結)。沙宣道的一段會於下個月完成。

Comments are closed.

    Archives

    October 2022
    September 2022
    August 2022
    June 2022
    May 2022
    April 2022
    February 2022
    January 2022
    October 2021
    September 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    August 2020
    June 2020
    May 2020
    October 2019
    June 2018
    April 2018
    March 2017
    February 2017
    June 2016
    February 2016
    June 2015
    May 2014

    Categories

    All

    RSS Feed

SUBSCRIBE E-NEWSLETTER 登記接收區內最新消息

* indicates required

Follow Paul


@2021 Office of District Councillor Paul Zimmerman
All rights reserved